SC 277 NB Bridge Replacement over I-77

Richland County

SCDOT proposes to replace the bridge along SC 277 Northbound over I-77 in Richland County. This design-build project consists of all work necessary to remove the existing bridge and to construct a new bridge, including the associated roadway and drainage work necessary to tie the new approaches to the existing roadway.

Notice to Potential Proposers

SC277 Pre-RFQ Meeting Slides (10/31/17)
Open-Forum Meeting SCBO Notice (10/18/17)


Attachment B - Supplemental Project Design Criteria

Environmental

  1. Categorical Exclusion - SC 277 (10/18/17)

Hazardous Materials

  1. Asbestos & Lead-Based Paint Report (2/13/18)

Hydraulics

  1. Toe Ditch Detail (2/13/18)

Roadway

  1. Drawing 805-710-SP (2/13/18)

Structures

  1. Rigid_Barrier_Adjacent_to_Wall (2/13/18)

Project Information Package

Environmental

  1. I-77 Permit Files (2/13/18)

Geotechnical

  1. Geotechnical Base Line Report (2/13/18)
  2. Boring Logs (2/13/18)
  3. Raw CPT Data (2/13/18)

Hydraulics

  1. SCDHEC Permitting Time (2/13/18)
  2. Drainage Files (5/9/18)

Roadway

  1. SC277 Concpt Design Files (2/13/18)
  2. I-77 Design Files (2/13/18)

Structures

  1. SI&A Report - SC 277 (10/18/17)

Survey

  1. I-77 Pavement Scan (2/13/18)
  2. I-77 Survey Files (2/13/18)

Utilities

  1. I-77 DB Utility Coordination (4/3/18)

Proposal Evaluation Team Meeting

A SC 277 NB over I-77 Bridge Replacement Committee meeting will be held on September 4, 2018 at 8:30 am at SCDOT Headquarters in Room G-14.
SC277 RFP Evaluation Committee Meeting (08/31/18)

Proposal Evaluation Committee Meeting

A SC 277 NB Over I-77 Bridge Replacement Committee meeting will be held on August 8, 2018 at 9:00 am at SCDOT Headquarters in Room 421.
SC 277 NB Over I-77 RFP Distibution Meeting Agenda (08/07/18)

Statement of Qualifications Evaluation Team Meetings

A SC 277 Bridge Replacement SOQ Evaluation Committee Meeting will be held on January 4th, 2018 at 11:00 AM at SCDOT Headquarters in Room 421.
SOQ Evaluation Committee Meeting Agenda - Distribution (01/02/18)

A SC 277 Bridge Replacement SOQ Evaluation Committee Meeting will be held on January 30th, 2018 at 08:30 AM at SCDOT Headquarters in Room G-14.
SOQ Evaluation Committee Meeting Agenda - Evaluation (01/02/18)

Notice to Parties Interested in Providing Design Build Services

Qualifications and/or proposals from any contracting entity must utilize the new ProjectWise electronic proposal submission system. The following information describes the process that teams should follow to access the SCDOT ProjectWise environment for proposal submissions and their respective project data using the new system. Please use this ProjectWise Account Setup & Requirements link to set up accounts.